Start-up date | Introduction of equipment and the installation location |
---|---|
25.11.2003 - 10.06.2022 | Power Supplies BP2407 in the amount of 374 pcs. for mine electric locomotives lighting circuits. |
10.12.2003 - 29.11.2017 | Batching control equipment «AUD-Dnipro» (mine normal construction), mine them. Lenina, Gvardeyskaya mine, Rodina mine, Oktyabr'skaya mine. |
23.09.2005 - 03.12.2014 | Equipment of the control register «AKR-Dnipro», Gvardeyskaya mine, Rodina mine. |
11.06.2004 - until now * | Signaling, centralization and blocking equipment «SZB-Dnipro», mine them. Lenina, Gvardeyskaya mine, Rodina mine, Oktyabr'skaya mine. |
05.12.2007 - 09.06.2021 | Power supplies BPA1203 in the amount of 60 pcs. for mine electric locomotives radio stations. |
15.02.2008 | Shaft signaling and communication equipment «ASHS-Dnipro» (mine normal construction), skip lifting, Rodina mine. |
03.12.2014 - 22.04.2015 | Shaft signaling and communication equipment for the sinking lift «ASHSP-Dnipro», Oktyabr'skaya mine. |
09.09.2013 - 01.09.2022 | Loud-speaking dispatcher communication equipment «AGDS-Dnipro», Rodina mine, Gvardeyskaya mine. |
14.03.2014 | Level control equipment «AKU-Dnipro» (mine normal construction), Oktyabr'skaya mine. |
30.01.2014 - 15.08.2022 | Shaft communication and signaling equipment «ASSS-Dnipro» (mine normal construction), mine them. Lenina, Gvardeyskaya mine, Oktyabr'skaya mine (6 sets). |
* - content of the equipment is constantly enlarging in line with the development of the horizon.